EnergyAustralia is continuing to provide good supply to the National Electricity Market.
- At Yallourn, Units 1, 2 and 3 are online and running. Unit 4 is offline for repairs.
- At Mt Piper, both units are running.
- EnergyAustralia’s gas assets at Hallett and Tallawarra A ran on Friday evening. Today, Newport, Jeeralang, Hallett and Tallawarra are available for market requirements.
- Tallawarra B, EnergyAustralia’s new gas-peaking power station, is continuing pre-commissioning works.