Key Points
- EnergyAustralia is providing good supply into the system.
- Two units are online at Yallourn power station in Victoria. A third unit is offline and expected to return to operation this evening. A fourth unit is undergoing repairs ahead of a planned outage commencing tomorrow. This unit is expected to return to service on 2 September.
- Mt Piper in New South Wales has both generating units operating at full capacity.
- Our gas assets at Tallawarra, Newport, Jeeralang and Hallett are operating to meet demand.
- Our team is working hard to keep pumping power into the system to support our 1.6 million customers.
-ends-
Background
Supporting customers
EnergyAustralia’s EnergyAssist program means the power won’t be disconnected and debt collection activities won’t be initiated. Residential customers on the program also have access to tailored payment plans, energy audits, information on grant programs and advice on energy usage.