EnergyAustralia continues to provide good supply to the National Electricity Market.

  • At Yallourn, all units are online and running.  
  • At Mt Piper, Units 1 and 2 are running.  
  • EnergyAustralia’s gas assets at Newport and Jeeralang are available for market requirements today. Tallawarra A may run this afternoon.  Hallett ran last night and this morning. 
  • Tallawarra B, EnergyAustralia’s new gas peaking power station, is online for synchronisation testing, ahead of hold point testing. Commercial operation expected in late February.